BLID Update 5.29
Work underway….
• The utility vaults installation along S. 7th to S. 9th on the eastside of Broadway will soon be set and adjusted.
• Roadway grading from 6th to 9th on Broadway.
• Sidewalks are being poured along S. 7th and on Broadway from 7th to 9th.
• Roadway paving on Broadway, from S. 6th to S. 7th and on S. 7th from Broadway to St. Helens is scheduled for mid-June.
• Large Power Vault being installed on S. 9th near the Pantages.
Questions? Concerns? Let me know.